EMV Calculator – Expected Monetary Value

Quick answer

The EMV calculator works out the expected monetary value of up to five project risks or opportunities by multiplying each impact by its probability and adding them up – a standard tool for risk analysis and contingency reserves.

%
$
%
$
%
$
%
$
%
$
Expected monetary value
$ —
Expected cost of threats
$ —
Expected value of opportunities
$ —
Suggested contingency reserve
$ —

Expected monetary value turns uncertain outcomes into a single figure. A risk with a 20% chance of costing $50,000 has an EMV of −$10,000. Adding all risks gives a sensible contingency reserve for a project.

How to use the EMV Calculator – Expected Monetary Value

  1. Risk 1 – probability
  2. Risk 1 – impact
  3. Risk 2 – probability
  4. Risk 2 – impact
  5. Risk 3 – probability
  6. Risk 3 – impact
  7. Risk 4 – probability
  8. Risk 4 – impact
  9. Risk 5 – probability
  10. Risk 5 – impact

Results update as you type, and every field accepts the units shown in its menu.

How it works

Enter the probability and the impact of each risk (negative for a cost, positive for a gain).

Tips

  • Use figures for the same period (a month, a quarter or a year) for every input so ratios compare like with like.
  • Track the metric over time – the trend usually tells you more than a single value.
  • Compare your result with industry benchmarks, which vary a lot between sectors.
  • Treat the result as a starting point for a decision, then check the assumptions behind each input.

Common mistakes to avoid

  • Mixing monthly and yearly numbers in the same calculation.
  • Using revenue where the formula needs profit (or the other way round).
  • Forgetting hidden costs such as taxes, fees, overheads or your own time.

Inputs explained

Field What to enter
Risk 1 – probability In %
Risk 1 – impact Amount in your currency
Risk 2 – probability In %
Risk 2 – impact Amount in your currency
Risk 3 – probability In %
Risk 3 – impact Amount in your currency
Risk 4 – probability In %
Risk 4 – impact Amount in your currency
Risk 5 – probability In %
Risk 5 – impact Amount in your currency

What each result means

  • Expected monetary value = ([Risk 1 – probability]×[Risk 1 – impact] + [Risk 2 – probability]×[Risk 2 – impact] + [Risk 3 – probability]×[Risk 3 – impact] + [Risk 4 – probability]×[Risk 4 – impact] + [Risk 5 – probability]×[Risk 5 – impact])÷100
  • Expected cost of threats = ([Risk 1 – probability]×min([Risk 1 – impact], 0) + [Risk 2 – probability]×min([Risk 2 – impact], 0) + [Risk 3 – probability]×min([Risk 3 – impact], 0) + [Risk 4 – probability]×min([Risk 4 – impact], 0) + [Risk 5 – probability]×min([Risk 5 – impact], 0))÷100
  • Expected value of opportunities = ([Risk 1 – probability]×max([Risk 1 – impact], 0) + [Risk 2 – probability]×max([Risk 2 – impact], 0) + [Risk 3 – probability]×max([Risk 3 – impact], 0) + [Risk 4 – probability]×max([Risk 4 – impact], 0) + [Risk 5 – probability]×max([Risk 5 – impact], 0))÷100
  • Suggested contingency reserve = max(-[Expected monetary value], 0)

Example values

How the main result changes when Risk 1 – probability changes and everything else stays at the example values above:

Risk 1 – probability (%) Expected monetary value
10 -6,200
15 -8,700
20 -11,200
25 -13,700
30 -16,200
40 -21,200

Formula

EMV = Σ (probability × impact)Threats are entered as negative impacts, opportunities as positive impacts

Worked example

Inputs — Risk 1 – probability: 20 %; Risk 1 – impact: $-50,000; Risk 2 – probability: 35 %; Risk 2 – impact: $-12,000; Risk 3 – probability: 10 %; Risk 3 – impact: $30,000; Risk 4 – probability: 0 %; Risk 4 – impact: $0; Risk 5 – probability: 0 %; Risk 5 – impact: $0.
Results — Expected monetary value = $-11,200.00; Expected cost of threats = $-14,200.00; Expected value of opportunities = $3,000.00; Suggested contingency reserve = $11,200.00.

Frequently asked questions

What is expected monetary value?

The probability-weighted average outcome of uncertain events.

Should threats be negative?

Yes – enter costs as negative numbers and gains as positive.

Is EMV the amount I will lose?

No – it is an average; any single risk either happens in full or not at all.

What formula does the EMV Calculator – Expected Monetary Value use?

EMV = Σ (probability × impact).