EMV Calculator (Expected Monetary Value)

Quick answer

The EMV calculator works out the expected monetary value of up to five project risks or opportunities by multiplying each impact by its probability and adding them up. It is a standard tool for risk analysis and contingency reserves.

%
$
%
$
%
$
%
$
%
$
Expected monetary value
$ -11,200.00
Expected cost of threats
$ -14,200.00
Expected value of opportunities
$ 3,000.00
Suggested contingency reserve
$ 11,200.00

Expected monetary value turns uncertain outcomes into a single figure. A risk with a 20% chance of costing $50,000 has an EMV of −$10,000. Adding all risks gives a sensible contingency reserve for a project.

How to use the EMV Calculator: Expected Monetary Value

  1. Risk 1: probability
  2. Risk 1: impact
  3. Risk 2: probability
  4. Risk 2: impact
  5. Risk 3: probability
  6. Risk 3: impact
  7. Risk 4: probability
  8. Risk 4: impact
  9. Risk 5: probability
  10. Risk 5: impact

Results update as you type, and every field accepts the units shown in its menu.

How it works

Enter the probability and the impact of each risk (negative for a cost, positive for a gain).

Inputs explained

Field What to enter
Risk 1: probability In %
Risk 1: impact Amount in your currency
Risk 2: probability In %
Risk 2: impact Amount in your currency
Risk 3: probability In %
Risk 3: impact Amount in your currency
Risk 4: probability In %
Risk 4: impact Amount in your currency
Risk 5: probability In %
Risk 5: impact Amount in your currency

What each result means

  • Expected monetary value = ([Risk 1: probability]×[Risk 1: impact] + [Risk 2: probability]×[Risk 2: impact] + [Risk 3: probability]×[Risk 3: impact] + [Risk 4: probability]×[Risk 4: impact] + [Risk 5: probability]×[Risk 5: impact])÷100
  • Expected cost of threats = ([Risk 1: probability]×min([Risk 1: impact], 0) + [Risk 2: probability]×min([Risk 2: impact], 0) + [Risk 3: probability]×min([Risk 3: impact], 0) + [Risk 4: probability]×min([Risk 4: impact], 0) + [Risk 5: probability]×min([Risk 5: impact], 0))÷100
  • Expected value of opportunities = ([Risk 1: probability]×max([Risk 1: impact], 0) + [Risk 2: probability]×max([Risk 2: impact], 0) + [Risk 3: probability]×max([Risk 3: impact], 0) + [Risk 4: probability]×max([Risk 4: impact], 0) + [Risk 5: probability]×max([Risk 5: impact], 0))÷100
  • Suggested contingency reserve = max(-[Expected monetary value], 0)

Example values

How the main result changes when Risk 1: probability changes and everything else stays at the example values above:

Risk 1: probability (%) Expected monetary value
10 -6,200
15 -8,700
20 -11,200
25 -13,700
30 -16,200
40 -21,200

Formula

EMV = Σ (probability × impact) Threats are entered as negative impacts, opportunities as positive impacts

Worked example

Inputs: Risk 1 – probability: 20 %; Risk 1 – impact: $-50,000; Risk 2 – probability: 35 %; Risk 2 – impact: $-12,000; Risk 3 – probability: 10 %; Risk 3 – impact: $30,000; Risk 4 – probability: 0 %; Risk 4 – impact: $0; Risk 5 – probability: 0 %; Risk 5 – impact: $0.
Results: Expected monetary value = $-11,200.00; Expected cost of threats = $-14,200.00; Expected value of opportunities = $3,000.00; Suggested contingency reserve = $11,200.00.

Frequently asked questions

What is expected monetary value?

The probability-weighted average outcome of uncertain events.

Should threats be negative?

Yes. Enter costs as negative numbers and gains as positive.

Is EMV the amount I will lose?

No. It is an average; any single risk either happens in full or not at all.