Burndown Chart Calculator

Quick answer

The burndown chart calculator tracks an agile sprint: it compares the story points burnt so far with the ideal burndown line and tells you whether the team is on track to finish the sprint.

days
Days elapsed
—
Points completed
—
Points remaining
—
Ideal remaining at this point
—
Points per day needed to finish
—
Average points per day so far
—
Status
—

A burndown chart plots the work left in a sprint against time. The ideal line falls in a straight line to zero on the last day. If actual remaining work sits above the line, the team is behind; below it, ahead.

How to use the Burndown Chart Calculator

  1. Sprint duration
  2. Total story points
  3. Points burnt each day so far

Results update as you type, and every field accepts the units shown in its menu.

How it works

Enter the sprint length, the total story points and the points completed each day so far.

Tips

  • Use figures for the same period (a month, a quarter or a year) for every input so ratios compare like with like.
  • Track the metric over time – the trend usually tells you more than a single value.
  • Compare your result with industry benchmarks, which vary a lot between sectors.
  • Treat the result as a starting point for a decision, then check the assumptions behind each input.

Common mistakes to avoid

  • Mixing monthly and yearly numbers in the same calculation.
  • Using revenue where the formula needs profit (or the other way round).
  • Forgetting hidden costs such as taxes, fees, overheads or your own time.

Inputs explained

Field What to enter
Sprint duration In days
Total story points A number
Points burnt each day so far A list of numbers separated by commas, spaces or new lines

What each result means

  • Days elapsed = count([Points burnt each day so far])
  • Points completed = sum([Points burnt each day so far])
  • Points remaining = [Total story points] – [Points completed]
  • Ideal remaining at this point = [Total story points]×(1 – [Days elapsed]÷[Sprint duration])
  • Points per day needed to finish = max([Total story points] – [Points completed], 0)÷max([Sprint duration] – [Days elapsed], 1)
  • Average points per day so far = [Points completed]÷max([Days elapsed], 1)

Example values

How the main result changes when Sprint duration changes and everything else stays at the example values above:

Sprint duration (days) Points remaining
5 30
7.5 30
10 30
12.5 30
15 30
20 30

Formula

Ideal remaining = total points × (1 − days elapsed ÷ sprint days)Actual remaining = total points − Σ points burntRequired pace = remaining ÷ days left

Worked example

Inputs — Sprint duration: 10 days; Total story points: 60; Points burnt each day so far: 5, 7, 4, 8, 6.
Results — Days elapsed = 5; Points completed = 30; Points remaining = 30; Ideal remaining at this point = 30; Points per day needed to finish = 6; Average points per day so far = 6; Status = On track or ahead.

Frequently asked questions

What is a burndown chart?

A graph of remaining work against time during a sprint.

What does it mean if I'm above the ideal line?

The team is behind schedule and may need to cut scope.

What is velocity?

The average story points a team completes per sprint.

What formula does the Burndown Chart Calculator use?

Ideal remaining = total points × (1 − days elapsed ÷ sprint days).

Sources

  1. Scrum.org – Scrum guide

Cite this calculator

Speedy Calculator. (2026). Burndown Chart Calculator. Speedy Calculator. https://speedycalculator.com/calculators/finance/burndown-chart/