A burndown chart plots the work left in a sprint against time. The ideal line falls in a straight line to zero on the last day. If actual remaining work sits above the line, the team is behind; below it, ahead.
How to use the Burndown Chart Calculator
- Sprint duration
- Total story points
- Points burnt each day so far
Results update as you type, and every field accepts the units shown in its menu.
How it works
Enter the sprint length, the total story points and the points completed each day so far.
Inputs explained
| Field | What to enter |
|---|---|
| Sprint duration | In days |
| Total story points | A number |
| Points burnt each day so far | A list of numbers separated by commas, spaces or new lines |
What each result means
- Days elapsed = count([Points burnt each day so far])
- Points completed = sum([Points burnt each day so far])
- Points remaining = [Total story points] – [Points completed]
- Ideal remaining at this point = [Total story points]×(1 – [Days elapsed]÷[Sprint duration])
- Points per day needed to finish = max([Total story points] – [Points completed], 0)÷max([Sprint duration] – [Days elapsed], 1)
- Average points per day so far = [Points completed]÷max([Days elapsed], 1)
Example values
How the main result changes when Sprint duration changes and everything else stays at the example values above:
| Sprint duration (days) | Points remaining |
|---|---|
| 5 | 30 |
| 7.5 | 30 |
| 10 | 30 |
| 12.5 | 30 |
| 15 | 30 |
| 20 | 30 |
Formula
Ideal remaining = total points × (1 − days elapsed ÷ sprint days)
Actual remaining = total points − Σ points burnt
Required pace = remaining ÷ days left
Worked example
Inputs: Sprint duration: 10 days; Total story points: 60; Points burnt each day so far: 5, 7, 4, 8, 6.
Results: Days elapsed = 5; Points completed = 30; Points remaining = 30; Ideal remaining at this point = 30; Points per day needed to finish = 6; Average points per day so far = 6; Status = On track or ahead.
Frequently asked questions
What is a burndown chart?
A graph of remaining work against time during a sprint.
What does it mean if I'm above the ideal line?
The team is behind schedule and may need to cut scope.
What is velocity?
The average story points a team completes per sprint.